Sunday 14 August 2011

One brick a day keeps the customer away

Its been a long time since our last post, there has been some significant delays on our site over the past two months with roughly six weeks + of elapsed idle time, however we were told this was due to the brick batch not being ready and a shortage of brick layers to do the work once they arrived.

Over the past four weeks the brickie team have been working on our site and the bricks have been going up very slowly, it seems almost like one brick a day kind of slow, but as long as its done professionally and were in before Christmas, it won't bother us so much.

We have also had the frame & pre-plaster stage inspections too during this period, with approximately 9 minor defects identified, we have been told that all of these items will be remediated which made us happy.